November Update

  • Concrete slabs have been poured on the elevated decks in the Library Media Center and Stair #3.

  • Light Gauge Metal Framing is being hung on the third level of the Library Media Center.

  • Brick is being installed on the site retaining walls and piers.

  • Elevator shaft in the Main Building is currently 14’W x 14’L x 13’D, and shoring for the 20-foot descent below grade continues to be installed for structural support and safety.