October Update

  • Steel framing and decking for Stair #3 have been erected and tied into the Library Media Center and Main Building.

  • Exterior walls are being built on the ground level.

  • Brick is being installed at the play area retaining walls.

  • Elevator shaft in the Main Building is currently 14’W x 14’L x 6’D, and shoring is being installed for the 20’ descent below grade.