September Update

  • Wall construction for Stair #3, which connects the existing main building to the new Library Media Center, is complete.

  • The cast-in-place concrete below the new Library Media Center is complete.

  • A new load-bearing wall on the West side of Stephens Hall has been constructed.

  • Hydro demolition continues in the new Main Building elevator shaft.