January Update

  • Structural steel erection is complete at the tie-in between Stephens Hall and the new Library Media Center. Steel decking has been installed, and final elevated concrete slabs have been poured.

  • Construction of the new playground is complete.

  • Turf systems have been installed on the north and south play areas; temporary fencing is in place, and both play areas are open and functional for school activities.

  • Interior and exterior light gauge metal framing is near completion; installation of the exterior sheathing has started.