March Update
Work is well underway at the Basilica School of St. Mary. Over the last month, the team has:
Demolished the existing storm line, which ran in front of Stephen’s Hall, and removed the old storm structures
Installed the new storm line and storm structures
Completed the clearing of trees, shrubbery, vegetation, etc., that was required to continue with construction
Began work on installing the scaffolding around the cupola that is needed to complete structural repairs